You’re managing a construction project to install several hundred air conditioner panels in a new office building. You have completed 350 panels out of a total of 900 planned panels, but according to your schedule you should have completed 400 of them. Your company’s contract states that you’ll be paid a fixed price of $75 per panel. You’ve spent $45,000 so far on the project. Which of the following BEST describes your situation?